M&E Services Design & Installation - Bikram Studio Liverpool

Original 'Hot Yoga' of Bikram Choudhury

Airtech in collaboration with equipment / controls manufacturers, designed, installed and commissioned a full fresh air gas fired Air Handling system including new supply and extract ductwork; attenuation and a stand alone Trend BMS Controls system.

Air Handling Unit

Air Handling Equipment Ltd in discussion with Airtech built the AHU, which was configured in the conventional manner and supplied in 6 sections for final assembly on site.

Control System

A new stand alone Trend 1Q3 Control System complete with the following items was installed:

1.       Panel mounted IQVIEW Keypad to allow monitoring and control of the system;

2.       Enable, fault and modulating controls to the Gas Fired Heater;

3.       Inverters for the AHU Supply and Extract Fans;

4.       Temperature Sensors in both studio and plant room.

Extract Ventilation

Extract ventilation systems consisting of in line fan c/w speed controller, grilles, louvers and associated duct was installed throughout WC and shower rooms.